March 12, 2019: Memorandum sent to NC Division of Energy, Mineral and Land Resources, NC DEQ
From: Dr. Jean Spooner, Chair, The Umstead Coalition
Reference: Mining Permit 92-10 - Modification Dated March 28, 2018 issued to Wake Stone Corporation. Request to reverse permit modification and re-instate Sunset Clause
We appreciate meeting with you on March 5, 2019 to discuss our objections to the above reference permit modification. Our objective was to further explain the basis for our request dated November 14, 2018 to reverse the permit modification to the Reclamation Condition 5.B. The Umstead Coalition letter was within 30 days of The Umstead Coalition’s discovery date (November 6, 2018) that the permit had been changed. There are no on-line records of the permit files.
From our discussion it is our understanding that your office issued the modification based on an e-mail in March 2018 from Wake Stone Corporation indicating a clerical error in the initial May 13 1981 mining permit (and all subsequent permits). Attached to the e-mail from Wake Stone Corporation was a document purportedly issued by the Mining Commission dated April 3, 1981, more than a month before the actual first permit issuance, which describes the permit conditions. DEQ staff may have assumed that the Mining Commission document has precedence and the 1981 permit was in error. However, DEQ acknowledged that an original of that Mining Commission document is not present in the permit file, and not verified.
Wake Stone Corporation did not submit a required permit modification request form prior to your issuing the 2018 modification.
Our first position is that the 1981 permit as written has precedence over the purported Mining Commission document dated over a month prior. The permit donation conditions were the result of negotiations over a period from January 27 to May 13, 1981 and are correctly written in the 1981 permit. The Mining Commission document dated a month before permit issuance, if valid, represents only one point in a long negotiation.
Please consider the following.
Second: Changing the word “sooner” to “later” in Section 5.B. is a SUBSTANTIAL change to the permit. This change eliminates the “Sunset Clause”, the right of the State of North Carolina to exercise its donation option 50 years after mining commenced. This change completely disadvantages William B. Umstead State Park and the State of NC.
Changing the text from “sooner” to “later” renders Section 5.B. meaningless. The plain reading of 5B requires the word “sooner” in order to have any utility/meaning in the permit. Otherwise, why would 5B have been in the permit for 38 years and a reference made to 50 years in the context of all quarryable stone not removed?
Third DEQ failed to follow its own procedures in issuing the modification. There was NO application from Wake Stone Corporation for a Permit Modification submitted for the change from “sooner” to “later.” Furthermore there was no notification to the affected landowners within 1,000 feet (NC Division of Parks and Recreation for William B. Umstead State Park), 2 private landowner as had occurred with other significant permit changes that affected Umstead State Park (e.g., change in the buffers, as evidence by extensive communications between NC Division of Parks and Recreation and DEQ in the permit file).
The 2018 permit modification in Section 5B of “sooner” to “later” was based upon an unverified document that was put into the permit file by Wake Stone Corporation. A Public Records request failed to show any original of this document. There has been no other due diligence by DEQ that the unverified document that Wake Stone added to the permit file was correct. An email referencing an unverified document that Wake Stone Corporation had put to the file should be considered insufficient grounds to make such a significant change to a permit. An unverified document should NOT override the actual first permit signed almost 1 month later. However, even if the document that Wake Stone Corporation added to the file is found to be correct, is should not take precedent over the permits signed by DEQ and Wake Stone Corporation over 37 years – the permits are the operating documents.
Finally, NC State Parks, local governments and the public depended on the 1981 Reclamation Conditions for 37 years before the 2018 DEQ modification. Even if the 1981 permit conditions are in error (which we content were not) the extraordinary length of time upon which these conditions were in effect render such an error inconsequential. The public has expected since the first permit was signed in May of 1981 that the State of NC has the option to exercise that could eliminate the large volume of heavy truck traffic, noise and dust at our most popular entrance to William B. Umstead State Park.
We strongly urge that Clause 5B in the Mining Permit 92-10 be corrected to the words used in the May 13, 1981 permit with the “sooner” word.
Download a PDF of the Umstead Coalition's letter to request return of Sunset Clause here.